S
SonOfPirate
I am trying to create a dynamic schedule for my project. I've set my Task
Type to Fixed Work and enter in a Work value. However, the default duration
"1 day?" remains regardless what I enter for the Work value. How can I setup
my project so that the duration defaults to a value reflective of the Work
value entered? In other words, if I enter 24 hours for Work, I would expect
the Duration to change to "3 days?".
This is a problem because it appears to be restricting the Finish Dates for
my tasks. Despite setting a task with 24 hours of Work, the project still
says it will be done in one day.
Type to Fixed Work and enter in a Work value. However, the default duration
"1 day?" remains regardless what I enter for the Work value. How can I setup
my project so that the duration defaults to a value reflective of the Work
value entered? In other words, if I enter 24 hours for Work, I would expect
the Duration to change to "3 days?".
This is a problem because it appears to be restricting the Finish Dates for
my tasks. Despite setting a task with 24 hours of Work, the project still
says it will be done in one day.