Problems with time period in PWA

O

Odd H Akerø

Being the Project Administrator in a norwegian company I
have set the week in Microsoft Project Web Access to start
on Monday, and that the timesheets should span a period
that is weekly. The number of weeks spanned is set to 1,
and resources should report their total hours worked for a
week. The method for reporting progress on tasks is:
Hours of work done per week and resources report the hours
worked on each task during each time period.
In the Tasks Page this works fine with the week starting
on Monday and ending on Sunday. In the Update Page and in
the Resource center, however, the week starts on Sunday
and ends on Saturday. Am I doing something wrong?
We are using Microsoft Project 2002 Professional.
 