A
Arthur
Hi
We have been running an implementation project for Project Server in our
company. We use Project Server 2003 and Project Pro 2003, both with latest
servicepacks. We have checked that all software has latest servicepacks as
part of the project. We used the EIF2002 for our implementation project, we
started out in september 2006, had pilot in january, rollout in february and
have been reporting all ours in Project Server from Mars. We use
administrative prosjects for none project time. Some groups have reported all
hours from january(pilot groups). Pilot did not result in any changes, thus
we continued on the same version for production. We do not use managed
timeperiods. We report "Hours of work done per day or per week", we only use
enterprise projects, we do not use master projects.
Recently(last two reporting sycles) we discovered problems in a few
projects. Hours(Actual work) not reported suddenly appeares in Project Pro
2003, when we check the timesheets we find these correct. In project Pro
several tasks is marked as completed, actual work is somehow set to equal to
work. Project Manager has not "messed" with percent complete.
Another problem is the administrative project, hours(actual work) reported
does not emerge in the administrative project when we open this in Project
Pro. Again the timesheet in PWA is correct.
Have anyone seen any problems like this before? What are we doing wrong? Can
we trust Project Server? Is there some way we can force the hours that we see
in PWA into the projects in Project Pro 2003?
/Arthur
We have been running an implementation project for Project Server in our
company. We use Project Server 2003 and Project Pro 2003, both with latest
servicepacks. We have checked that all software has latest servicepacks as
part of the project. We used the EIF2002 for our implementation project, we
started out in september 2006, had pilot in january, rollout in february and
have been reporting all ours in Project Server from Mars. We use
administrative prosjects for none project time. Some groups have reported all
hours from january(pilot groups). Pilot did not result in any changes, thus
we continued on the same version for production. We do not use managed
timeperiods. We report "Hours of work done per day or per week", we only use
enterprise projects, we do not use master projects.
Recently(last two reporting sycles) we discovered problems in a few
projects. Hours(Actual work) not reported suddenly appeares in Project Pro
2003, when we check the timesheets we find these correct. In project Pro
several tasks is marked as completed, actual work is somehow set to equal to
work. Project Manager has not "messed" with percent complete.
Another problem is the administrative project, hours(actual work) reported
does not emerge in the administrative project when we open this in Project
Pro. Again the timesheet in PWA is correct.
Have anyone seen any problems like this before? What are we doing wrong? Can
we trust Project Server? Is there some way we can force the hours that we see
in PWA into the projects in Project Pro 2003?
/Arthur