K
kas
We have been experiencing problems with data being out of synch, 0 Work
Remaining reappearing with odd numbers,and other Work (hours) related fields
displaying hours that cannot be tracked, or in some cases, PWA displaying 0
Work and the Project Plan displaying various numbers not synching with PWA.
It just occured to me that it may only be on Project Plans where I, as PS
Administrator/Coordinator, will log on as the PM User using the Project
Server Authenication and perform the Updates for them; or, in some cases when
a user becomes inactive, I will log on as that user, again using Project
Server Authenication, reactivate the account, and zero out Remaining Work.
Typically, Project Server Users log on using Windows Authentication, using
their Windows User Account.
Not all the time, but sometimes I will encounter the Cannot Create Manager
Account From Project Professional (0x8c04003c) Project Server Spooler error
when the Update Process gets to the point of opening Project to insert the
updates.
1. Do you think this could be the culprit of the out of synch data between
PS and Project?
2. Is this the correct process for processing Updates/Time for Project
Managers other than yourself? If not, is there a Best Practice?
Thank you.
Is this the p
Remaining reappearing with odd numbers,and other Work (hours) related fields
displaying hours that cannot be tracked, or in some cases, PWA displaying 0
Work and the Project Plan displaying various numbers not synching with PWA.
It just occured to me that it may only be on Project Plans where I, as PS
Administrator/Coordinator, will log on as the PM User using the Project
Server Authenication and perform the Updates for them; or, in some cases when
a user becomes inactive, I will log on as that user, again using Project
Server Authenication, reactivate the account, and zero out Remaining Work.
Typically, Project Server Users log on using Windows Authentication, using
their Windows User Account.
Not all the time, but sometimes I will encounter the Cannot Create Manager
Account From Project Professional (0x8c04003c) Project Server Spooler error
when the Update Process gets to the point of opening Project to insert the
updates.
1. Do you think this could be the culprit of the out of synch data between
PS and Project?
2. Is this the correct process for processing Updates/Time for Project
Managers other than yourself? If not, is there a Best Practice?
Thank you.
Is this the p