Prochain Question

I

iyerra

I am currently using Prochain for critical chain project management
(http://www.prochain.com).

I used the feature "Project Working Times" and set up the working hours
for my project to 6 hrs/day and identified that no work would be done
on weekends. In addition, I summarized that:

Hours per day: 6
Hours per week: 30
Days per month: 20

Then I ran the built-in macro "Prochain Steps 1, 2" and noticed the
following:

Task "Develop model" has a duration of 15 days, start 4/4, end 4/19.

The start and end dates for the tasks are automatically determined by
Prochain.

Is the end date accurately computed considering that I have specified
that no work is performed on weekends?

Thanks for sharing any feedback.
 