R
Roger
Is it advisable to baseline individual projects prior to linking them
into a master programme file or should baselining be handled at the
programme level?
How are changes made to individual projects during the week
highlighted in a master programme file?
Should dependencies be handled at the project level or at the master
programme level?
The reason for the questions is that there is a requirement for a
programme consolidation milestone report to be created and managed on
a weekly basis. I would like some 'heads-up' information about the
best way to begin to manage this.
Regards
Roger
into a master programme file or should baselining be handled at the
programme level?
How are changes made to individual projects during the week
highlighted in a master programme file?
Should dependencies be handled at the project level or at the master
programme level?
The reason for the questions is that there is a requirement for a
programme consolidation milestone report to be created and managed on
a weekly basis. I would like some 'heads-up' information about the
best way to begin to manage this.
Regards
Roger