Progress Against Plan Gantt Chart

G

Ginger

Hi..

I am in desperate need to help with some analysis. I am reviewing the Gantt
Chart and have noticed that I have rolled up summary tasks that show the
progress to be 1-2 months behind the "current" date. However, there are no
late tasks and the progress of the detailed tasks appear to be progress as
needed. I cannot figure out why the Gantt Chart is displaying the results
that it is. I have attached a summary task and detailed information in hopes
that someone can help me resolve or explain this issue. EDB is the higher
summary task with the Create PSD, PSD Approvals, PSD Submission, and
Conversion Program are summaries as well under EDB.

PERCENT SUMMARY TASK DURA WORK START FINISH
77% EDB 198 days 594.5 hrs 07/06/05 04/18/06
100% Create PSD 137 days 245 hrs 07/06/05 01/23/06
100% PSD Approvals 7 days 14 hrs 01/23/06 02/01/06
100% PSD Submission 12 days 80.5 hrs 02/02/06 02/17/06
10% Conversion Program 31 days 200 hrs 03/03/06 04/14/06
 