Ginger
Hi All,
I am in desperate need of help as I am stumped!! I am reviewing a summary
tasks progress for a group of tasks using the Gantt Chart view and cannot
figure out why it is calculating the way it is.
I have a summary task that appears as if it is 1-2 months behind schedule
however there are no late tasks and the detailed tasks are moving along. I
have attached the list of task, their percente completes and dates.
PERCENT SUMMARY TASK DURATION WORK START FINISH
77% EDB 198 days 594.5 hrs 07/06/05 04/18/06
100% Create PSD 137 days 245 hrs 07/06/05 01/23/06
100% PSD Approvals 7 days 14 hrs 01/23/06 02/01/06
100% PSD Submission 12 days 80.5 hrs 02/02/06 02/17/06
10% Conversion Program 31 days 200 hrs 03/03/06 04/14/06
I am in desperate need of help as I am stumped!! I am reviewing a summary
tasks progress for a group of tasks using the Gantt Chart view and cannot
figure out why it is calculating the way it is.
I have a summary task that appears as if it is 1-2 months behind schedule
however there are no late tasks and the detailed tasks are moving along. I
have attached the list of task, their percente completes and dates.
PERCENT SUMMARY TASK DURATION WORK START FINISH
77% EDB 198 days 594.5 hrs 07/06/05 04/18/06
100% Create PSD 137 days 245 hrs 07/06/05 01/23/06
100% PSD Approvals 7 days 14 hrs 01/23/06 02/01/06
100% PSD Submission 12 days 80.5 hrs 02/02/06 02/17/06
10% Conversion Program 31 days 200 hrs 03/03/06 04/14/06