A
Andrew
I am trying to incorporate two progress charts in one msp file. An active
progress chart and a static progress chart. The active is the standard
tracking gantt that comes with msp with an amended table to compare planned %
against actual %. The static chart is easy if in a separate file - I baseline
the project and change the activity bars to baseline start and finish, rather
than start and finish. I then change the progress bar to Baseline start to
complete throughout. If I record the actual starts and finishes in a dummy
field ie start1 etc this works fine. However if i put this view in the same
file as the active chart, the progress bar works but re-aligns itself to the
actual starts and finishes, so sometimes the bar goes beyond the "planned"
bar if behind programme or finishes before the "planned" bar if completed
ahead of programme. What I want it to do is to stay within the baseline bar -
any ideas
progress chart and a static progress chart. The active is the standard
tracking gantt that comes with msp with an amended table to compare planned %
against actual %. The static chart is easy if in a separate file - I baseline
the project and change the activity bars to baseline start and finish, rather
than start and finish. I then change the progress bar to Baseline start to
complete throughout. If I record the actual starts and finishes in a dummy
field ie start1 etc this works fine. However if i put this view in the same
file as the active chart, the progress bar works but re-aligns itself to the
actual starts and finishes, so sometimes the bar goes beyond the "planned"
bar if behind programme or finishes before the "planned" bar if completed
ahead of programme. What I want it to do is to stay within the baseline bar -
any ideas