R
Rocky
Hello!
I have a project that seems to be set up and leveled
properly and I'm wondering how to best handle a certain
situation. For example, if I have a resource that elects
to work 10 hours on a given 20-hour task during a non-
working time (e.g., he works 10 hours on a Saturday to
get ahead), how do I best update my project to show this
progress against the task that's not scheduled to be
worked on for weeks from now? If I just go to the percent
complete and enter 50%, the downstream tasks don't show a
benefit from that "free" progress. I know I can just
change the task Duration or Work to be 10 hours instead
of 20 and the downstream tasks will update properly, but
then my project doesn't reflect reality. I want to show
that the task is still a 20 hour task, but without
impacting the schedule, someone performed 10 hours of the
20.
It seems like this would be a simple, common event but
I'm at a loss as to how I should address it.
I have a project that seems to be set up and leveled
properly and I'm wondering how to best handle a certain
situation. For example, if I have a resource that elects
to work 10 hours on a given 20-hour task during a non-
working time (e.g., he works 10 hours on a Saturday to
get ahead), how do I best update my project to show this
progress against the task that's not scheduled to be
worked on for weeks from now? If I just go to the percent
complete and enter 50%, the downstream tasks don't show a
benefit from that "free" progress. I know I can just
change the task Duration or Work to be 10 hours instead
of 20 and the downstream tasks will update properly, but
then my project doesn't reflect reality. I want to show
that the task is still a 20 hour task, but without
impacting the schedule, someone performed 10 hours of the
20.
It seems like this would be a simple, common event but
I'm at a loss as to how I should address it.