R
Robb6
I have my cacluation set to manual and these three checked in under
caclulation options:
Move end of completed parts after status date back to status date.
And move start of remaining parts back to status date.
Move start of remaining parts before status date forward to status
date.
I did not check this one under options:
And move end of completed parts forward to status date.
I have also allowed tasks to split.
When I F9 to cacluate I still have progress forward of the status
date. When I use Update Project under Tracking I still get progress
drawn forward of the status date.
I am using a simple %complete tracking method and can not figure out
why I have progress forward of my status date.
Please help.
caclulation options:
Move end of completed parts after status date back to status date.
And move start of remaining parts back to status date.
Move start of remaining parts before status date forward to status
date.
I did not check this one under options:
And move end of completed parts forward to status date.
I have also allowed tasks to split.
When I F9 to cacluate I still have progress forward of the status
date. When I use Update Project under Tracking I still get progress
drawn forward of the status date.
I am using a simple %complete tracking method and can not figure out
why I have progress forward of my status date.
Please help.