soe soe
i have a summary task which contains two tasks;
task-1 10-Apr to 17-Apr 100% complete
task-2 20-May to 25-May 0% complete
when I draw progress line on 18-May, the progress point of summary task goes
to 17-Apr which, in managers' view, is late. I want to show the summary
progress point (red-dot) to 20-May instead.
How can I do it?
task-1 10-Apr to 17-Apr 100% complete
task-2 20-May to 25-May 0% complete
when I draw progress line on 18-May, the progress point of summary task goes
to 17-Apr which, in managers' view, is late. I want to show the summary
progress point (red-dot) to 20-May instead.
How can I do it?