F
FleurH
I have a question about progress lines. In my project plan, I have a number
of external dependencies (deliveries into the project in fact). I have
entered these as milestones to make it easy to track them, and grouped them
under a summary taskline. Each dependency is tied to at least one task as
'finish-to-start', as these are tasks that cannot start without the
dependency being delivered. Note that these linked tasks are under other
summary tasks.
When I try to use progress lines to show the status of my plan, for some
reason the progress line fails to properly calculate the progress for the
milestone summary taskline. The reason seems to be that although each
milestone is marked as 0 days duration, the summary task duration is
calculated as the period from the first milestone to the last one - so for
example if my first milestone is 5/Dec/05 and the last is 1/May/06, the
summary milestone taskline has a duration of 105 days - and although I may
mark a milestone under the summary taskline as 100% complete, this does not
reduce the number of days on the summary taskline. Hence the progress line
always shows that there are 105 days left to complete the 'tasks'. The
progress line does correctly recognise that an individual milestone has been
delivered, and draws through the milestone itself.
Is there a way of correcting for this?
Fleur Howles
of external dependencies (deliveries into the project in fact). I have
entered these as milestones to make it easy to track them, and grouped them
under a summary taskline. Each dependency is tied to at least one task as
'finish-to-start', as these are tasks that cannot start without the
dependency being delivered. Note that these linked tasks are under other
summary tasks.
When I try to use progress lines to show the status of my plan, for some
reason the progress line fails to properly calculate the progress for the
milestone summary taskline. The reason seems to be that although each
milestone is marked as 0 days duration, the summary task duration is
calculated as the period from the first milestone to the last one - so for
example if my first milestone is 5/Dec/05 and the last is 1/May/06, the
summary milestone taskline has a duration of 105 days - and although I may
mark a milestone under the summary taskline as 100% complete, this does not
reduce the number of days on the summary taskline. Hence the progress line
always shows that there are 105 days left to complete the 'tasks'. The
progress line does correctly recognise that an individual milestone has been
delivered, and draws through the milestone itself.
Is there a way of correcting for this?
Fleur Howles