A
Andrew
Good Morning
I have had a progressed chart sent to me that does not work. The chart has
been rescheduled from 03.12.08, and the button in tracking for reschedule
uncompleted work from has been set as 03.12.08. When I reschedule the bar in
question goes beyond the christmas break. the %complete is 30 there is only
one predessesor which was complete in november (FS). There is a massive gap
between the start of the bar and the remaining bar which does represent 10
days ie 70% Why is there such a gap and why does it not restart from 03.12.08
Any help would be appreciated, as we cannot issue this at the moment.
Many Regards
Andrew
I have had a progressed chart sent to me that does not work. The chart has
been rescheduled from 03.12.08, and the button in tracking for reschedule
uncompleted work from has been set as 03.12.08. When I reschedule the bar in
question goes beyond the christmas break. the %complete is 30 there is only
one predessesor which was complete in november (FS). There is a massive gap
between the start of the bar and the remaining bar which does represent 10
days ie 70% Why is there such a gap and why does it not restart from 03.12.08
Any help would be appreciated, as we cannot issue this at the moment.
Many Regards
Andrew