M
ma.u
Hi,
I use Project 2003 on Oracle 9 database, and I created some triggers
on
MSP_TASKS and MSP_PROJECTS for keep syncronized project data with an
another
database.
When I save sometimes Project say me to check data, but these are data
that
IT load from db and adjust (I set EXT_EDITED_??? fields); sometimes it
delete
all tasks.
Looking in msp_tasks i see that the tasks i need have another proj_id
(code of temporary project used by MSProject during save).
Why MSP change proj_id of my tasks?
Thanks
I use Project 2003 on Oracle 9 database, and I created some triggers
on
MSP_TASKS and MSP_PROJECTS for keep syncronized project data with an
another
database.
When I save sometimes Project say me to check data, but these are data
that
IT load from db and adjust (I set EXT_EDITED_??? fields); sometimes it
delete
all tasks.
Looking in msp_tasks i see that the tasks i need have another proj_id
(code of temporary project used by MSProject during save).
Why MSP change proj_id of my tasks?
Thanks