B
Bruce McF
When building a custom formula to find working days between two dates, trying
to use the Formula in the Summary calculation explodes. Using the rollup
Maximum works fine.
With this workaround, I am fine, but was wondering if I was doing something
wrong when trying to simply use the formula in the Summary/Group. I tried
putting the ProjDateDiff formula in Duration1 and Number1 and Project crashes
whenever I tried to use the formula for the summary of the custom field.
(Sorry, I was trying to get this in the main forum.)
to use the Formula in the Summary calculation explodes. Using the rollup
Maximum works fine.
With this workaround, I am fine, but was wondering if I was doing something
wrong when trying to simply use the formula in the Summary/Group. I tried
putting the ProjDateDiff formula in Duration1 and Number1 and Project crashes
whenever I tried to use the formula for the summary of the custom field.
(Sorry, I was trying to get this in the main forum.)