K
Kurt Verhaegen
In Project Professional you'll have ProjdurConv which you can use in a
formule in a custom field. I want to have this functionality available in
VBA to have a correct interpretation of input in the work column on the
projectbeforetaskchange event.
The problem is that the newval of this event returns what the user has typed
in, which can be 2, 2h, 2 h, 120min, or even for a different language 2u.
Anybody a clue how to handle this problem of conversion?
Grtz, Kurt
formule in a custom field. I want to have this functionality available in
VBA to have a correct interpretation of input in the work column on the
projectbeforetaskchange event.
The problem is that the newval of this event returns what the user has typed
in, which can be 2, 2h, 2 h, 120min, or even for a different language 2u.
Anybody a clue how to handle this problem of conversion?
Grtz, Kurt