I have been asked to create a view with 2005 completed projects
including baseline finish and actual finish. The fields I need to see
in the Portfolio Analyzer is the Finish date fields. What must I do to
add these fields? I have been reading posts and from what I see I will
need to set up Enterprise Outline fields and set them equal to the
baseline and actual finish fields... is that right? I find the
Analyzer powerful in some ways yet lacking important fields. I am
using Project 2002 Server.