J
JimS
I am building a project file that has roughly 200 inputs that are
driving roughly 400 tasks. The project ultimately must finish on a
specified date. I need the 400 tasks to be completed as soon as
possible in order to meet the deadline. For the sake of other teams
providing the inputs, I need to define the latest date in which the
inputs can be provided and not affect the deadline to my project.
Please advise how I can set up the project.
My approach was to define the Inputs with a constraint of "As Late As
Possible" and the tasks with a constraint "As Soon As Possible". The
approach assumed that if an input was linked as a predecesor to a task,
the task duration would push back the Finish Date of the input in order
to meet the deadline. This worked some of the time, but some of the
inputs have a very late Finish Date causing the task to go beyond the
project deadline. I noticed that there are resources that are sitting
idle between tasks because of this late delivery of some inputs.
Any thoughts / suggestions apart from forcing the inputs to be
available on random dates until everything simply "works out"?
driving roughly 400 tasks. The project ultimately must finish on a
specified date. I need the 400 tasks to be completed as soon as
possible in order to meet the deadline. For the sake of other teams
providing the inputs, I need to define the latest date in which the
inputs can be provided and not affect the deadline to my project.
Please advise how I can set up the project.
My approach was to define the Inputs with a constraint of "As Late As
Possible" and the tasks with a constraint "As Soon As Possible". The
approach assumed that if an input was linked as a predecesor to a task,
the task duration would push back the Finish Date of the input in order
to meet the deadline. This worked some of the time, but some of the
inputs have a very late Finish Date causing the task to go beyond the
project deadline. I noticed that there are resources that are sitting
idle between tasks because of this late delivery of some inputs.
Any thoughts / suggestions apart from forcing the inputs to be
available on random dates until everything simply "works out"?