R
Rebecca
I've created a new project. When I assign resources to my
tasks the hours that the resource is allocated are not
correct. What I want the program to do is calulate a
percentage of the allocated hours for the task to more
than one resource. What happens is that I was using
percentage as my unit measure in the resource and then
changed it to decimal. But the amounts for ea resource are
still not correct.
What do I need to do to have my resources hours calculate
correctly for each based on their percentage that I
entered?
tasks the hours that the resource is allocated are not
correct. What I want the program to do is calulate a
percentage of the allocated hours for the task to more
than one resource. What happens is that I was using
percentage as my unit measure in the resource and then
changed it to decimal. But the amounts for ea resource are
still not correct.
What do I need to do to have my resources hours calculate
correctly for each based on their percentage that I
entered?