Project 2000

M

mjdehan

I have an existing project and I am trying to change the calendar to one that
recognizes the non-working Holidays sanctioned by my company. Everytime I
effect that change and try to save, I get the following message:
"Winproj.exe has generated errors and will be closed by Windows. You will
need to restart the program." If I don't change the calendar, any other
changes are accepted. Any ideas?
 
M

Mike Glen

Hi mjdehan,

Welcome to this Microsoft Project newsgroup :)

I've not come across this before. It could be corruption of some sort. You
could try re-installing Project or, if you suspect a corrupt file, you could
try the suggestions in FAQ Item: 43. File Bloat? - Might be Corruption.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/.

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 