I've got a project in about 200-300 lines worth of activity occuring at four
locations. For the most part, the operations are sequential.
Location 1: Orders Parts
Location 2: Assembles Parts
Location 3: Paints Parts
Location 4: Manages Project
I've got about 30 assemblies to track through this process.
I'd like for each organization to manager their own part of the schedule.
Would the best way to do that be to create a Master and several
sub-projects?
I'd then have each organization email me their sub-project, dump it to a
folder on our server, and load the updates in the Master project.
I'm kind-of new at this. Does this approach make sense?
locations. For the most part, the operations are sequential.
Location 1: Orders Parts
Location 2: Assembles Parts
Location 3: Paints Parts
Location 4: Manages Project
I've got about 30 assemblies to track through this process.
I'd like for each organization to manager their own part of the schedule.
Would the best way to do that be to create a Master and several
sub-projects?
I'd then have each organization email me their sub-project, dump it to a
folder on our server, and load the updates in the Master project.
I'm kind-of new at this. Does this approach make sense?