Project 2002 special report needed

J

Joe

In my project I have many tasks, sub-tasks, sub-sub-tasks,
etc.

I want to make a "to do" list for each resource that lists
the task hierarchy. In other words I want my report to
look like this:

Resource: John Doe
Week: 12/1/03 to 12/5/03
Task ABC
..sub task jkl
...sub task xyz design work - 8 hrs
Task GHI
..sub taks srt
...sub task tuv design work - 4 hours

The default reports do not give me the task hierarchy and
makes it difficult for the resource to figure out what he
needs to do.
 
M

Mike Glen

Hi Joe,

Welcome to this Microsoft Project newsgroup :)

I think this is candidate for some vba code - try the developer ng. Please
note the new Project newsgroup arrangements repeated in FAQ 24 - Project
Newsgroups, as this one is closing down. FAQs, companion products and other
useful Project information can be seen at this web address:
<http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top