Brian
I am trying to figure out the best way to have Project
automatically place a specific task on a day of week. For
example:
Task A begins on Monday, October 20 and is 82 hours in
duration. I have 2 resources that are working 8 hour days
Monday through Friday. The end date for Task A is on
Monday, October 27.
Task B must start after Task A finishes, but it also must
start on the Sunday following the completion of Task A.
So, Task B in the scenario above should be forced to start
on Sunday, November 2. If I add a resource to Task A,
then Task A will finish in the middle of the week of
October 20 so task B should start on Sunday, October 26.
Is there a way to have Project setup this type of scenario?
Thanks in advance!
Brian
automatically place a specific task on a day of week. For
example:
Task A begins on Monday, October 20 and is 82 hours in
duration. I have 2 resources that are working 8 hour days
Monday through Friday. The end date for Task A is on
Monday, October 27.
Task B must start after Task A finishes, but it also must
start on the Sunday following the completion of Task A.
So, Task B in the scenario above should be forced to start
on Sunday, November 2. If I add a resource to Task A,
then Task A will finish in the middle of the week of
October 20 so task B should start on Sunday, October 26.
Is there a way to have Project setup this type of scenario?
Thanks in advance!
Brian