R
RachelN
Our problem in Project is that we have a main task and several
underlying tasks that carry various weights that add up to 100% of the
main task. We are looking to apply some kind of weight to a subtask
that when it adds up to 100% of the subtask it will affect a weighted
percentage of the main task. We want each subtask to be adjustable
based on its' weighted value.
Example:
Main task 100% when five subtasks are completed. We are using %
Complete column to track inside Project.
Subtask one is worth 10% of the total main task
Subtask two is worth 20% of the total main task
Subtask three is worth 15% of the total main task
Subtask four is worth 20% of the total main task
Subtask five is worth 35% of the total main task
underlying tasks that carry various weights that add up to 100% of the
main task. We are looking to apply some kind of weight to a subtask
that when it adds up to 100% of the subtask it will affect a weighted
percentage of the main task. We want each subtask to be adjustable
based on its' weighted value.
Example:
Main task 100% when five subtasks are completed. We are using %
Complete column to track inside Project.
Subtask one is worth 10% of the total main task
Subtask two is worth 20% of the total main task
Subtask three is worth 15% of the total main task
Subtask four is worth 20% of the total main task
Subtask five is worth 35% of the total main task