Project 2003 - Blocking View of Tasks

W

Walter

I have a large project and would like to block viewing access of several
subtask and therir assiciated tasks.
This is so I send it out and not have others see the details.
 
R

Rod Gill

Hi,

Insert a flag column such as Flag1. Set to Yes all tasks that you want to
hide, then create a new filter to show all tasks with Flag1 set to No.

This will work, but if you send a .mpp file, they can see all tasks by
showing the filter All Tasks again.

You could send and html file (File, save as web page) and by creating a new
map select tasks with your Flag1=No filter. That will make sure your
'secret' tasks don't go.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.project-systems.co.nz/
Email rodg AT project-systems DOT co DOT nz
 