Is it possible to set up the Standard Project Calendar to reflect a 4-4-5
accounting calendar? If so, how do I do it?
For example, the Standard Calendar in Project for June 2010 is from June
1st-June 30th. The accounting calendar for the month of June 2010 begins May
31st-July 4th.
Thanks,
AK