Project 2003 - Can a default be set to start each task at 8:00 AM

D

Dick4b

With fixed work tasks, split among several different types of resources, the
allocated hours are often fractional and the finish times are set down to the
minute. Project will schedule a successor task to start the minute after the
current task completes. It is highly unlikely, for instance, that I or a
group of resosurces will start a new task at 4:46 PM (work day ends at 5:00
PM) when the previous task completes at 4:45 PM. Starting fresh in the
morning is more the norm. Can Project be enabled to start each new task at
8:00 AM, regardless of the time of finish of the preceeding task? Setting a
'Start no Earlier Than' constraint will work initially but would have to be
adjusted any time a scheduled date moves to the right.
 
R

Renaud Duisit

I could never get around that one. Any help would be appreciated. Though I do
not think it would be possible for now in Project.
:eek:(
 
J

JulieD

Hi

i've used a little "trick" occassionally in a project to force a task to
move to a certain time, but i don't know how to do it for every task.

What i've done is create a new calendar that has a working time of 1minute
(8am to 8.01 am)
then when i've had to "force" a task to move say to the next morning i've
added a task (Task A) between this task (Task 2) and it's predecessor (Task
1) with the duration of 1 minute and then assigned the calendar to it ..
this makes the TaskA go to 8am on the next day and then Task 2 follows it. -
you can then change row height & format the row so it can't been seen when
printing - but as i said, it wouldn't be a solution if you had to do it for
every task in the project

Cheers
JulieD
 
M

Mike Glen

Hi Dick,

Welcome to this Microsoft Project newsgroup :)

It can't be done reasonably in Project. However, I believe you could be
guilty of overmanaging to want this level of detail:) Give the tasks to the
resources and let them manage their own time within reasonable limits.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top