Susan L.
I'm a little 'rusty' using MSProject ... How would I enter a task with a
fixed duration (would take 15 days from start to finish), but where the
actual work (by the resource) would be less, say only 3 days of actual work
spread over that that 15 day period - so less than full time for the
resource, but ONLY on this task.
Thank you.
Susan