project 2003 - Fixed duration - Less effort (work) required

S

Susan L.

I'm a little 'rusty' using MSProject ... How would I enter a task with a
fixed duration (would take 15 days from start to finish), but where the
actual work (by the resource) would be less, say only 3 days of actual work
spread over that that 15 day period - so less than full time for the
resource, but ONLY on this task.

Thank you.

Susan
 
J

Jan De Messemaeker

Hi Susan,

Enter the duration
Insert a column Work
Enter the work
Make the task type Fixed duration
assign the resource

There are other ways...
Hope this helps
 
S

Susan L.

Thank you, Jan! That accomplishes what I want.

Jan De Messemaeker said:
Hi Susan,

Enter the duration
Insert a column Work
Enter the work
Make the task type Fixed duration
assign the resource

There are other ways...
Hope this helps
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top