When exporting from Project 2003 to Excel, I encountered a Bug with the Task
Names. First, there is no "Task Names" field in the mapping table, just
"Names",. When this is chosen, the generated Excel file has the expected rows
for each of the tasks. Interspersed are rows where the Resource Names from
the previous task are shown as the Task Name (as well as the resource name).
Essentially, each task with an assigned resource generates two resource lines
in the Excel file: the correct one and one with the Resource Name appearing
as the Task Name.
This is a simple Microsoft Bug.
Names. First, there is no "Task Names" field in the mapping table, just
"Names",. When this is chosen, the generated Excel file has the expected rows
for each of the tasks. Interspersed are rows where the Resource Names from
the previous task are shown as the Task Name (as well as the resource name).
Essentially, each task with an assigned resource generates two resource lines
in the Excel file: the correct one and one with the Resource Name appearing
as the Task Name.
This is a simple Microsoft Bug.