T
Tom L
I've been reading through the Managing Enterprise Projects book by
Gary Chefetz and Dale Howard along with the Project 2003 resource kit
documentation but have a few questions I hope you'll be able to help
me with.
1. Reading some previous posts here regarding task predecessors, it
seems as if Project 2003 is not capable of only displaying tasks in PWA
which have had all their predecessors completed. Is there any part of
the Project 2003 resource kit documentation which explains this? In
some cases it will be physically impossible to start a task which
relies on it's predecessor being completed, so we don't want to clutter
the users task list with tasks they can not even start on yet.
2. If it comes down to a training issue and the users having to notify
the task successors resource, this will lead to even more
administration and disrupt the workflow of the project. Is there a way
to automate the notification of completed tasks, how about
customisation?
3. Is it possible to view all the tasks in all the projects which are
overdue by customising views? Is this possible in PWA?
Any help with these issues would be much appreciated.
Many thanks,
Tom
Gary Chefetz and Dale Howard along with the Project 2003 resource kit
documentation but have a few questions I hope you'll be able to help
me with.
1. Reading some previous posts here regarding task predecessors, it
seems as if Project 2003 is not capable of only displaying tasks in PWA
which have had all their predecessors completed. Is there any part of
the Project 2003 resource kit documentation which explains this? In
some cases it will be physically impossible to start a task which
relies on it's predecessor being completed, so we don't want to clutter
the users task list with tasks they can not even start on yet.
2. If it comes down to a training issue and the users having to notify
the task successors resource, this will lead to even more
administration and disrupt the workflow of the project. Is there a way
to automate the notification of completed tasks, how about
customisation?
3. Is it possible to view all the tasks in all the projects which are
overdue by customising views? Is this possible in PWA?
Any help with these issues would be much appreciated.
Many thanks,
Tom