1. I have put a calculated field in the report header.
It does not reflect the value that I see on the Table View of the data, but
shows 0.
When you do that, is it the first/last/min/max value of the calculated field.?

2. What happens to Calculated fields on Summary Tasks - are they recalculated?
 
J

Jack Dahlgren

Which report? Perhaps you inserted a project level field instead of a task
level field?

Can you detail the steps you took and which custom field you are inserting?

That would help to troubleshoot.

Generally the behavior of custom field formulas for summary task is to do
nothing, but you can set it to calculate as min, max sum etc. or use the
formula.
This is done in the same customize fields dialog box where you choose
formula or value list.

-Jack Dahlgren
 