K
Katie
I have seen this several times, but do not know a solution.
Project 2003 files seem to randomly delete the data from tasks, so that the
entire task row becomes blank. Filtering it does not show the task as
actually blank, but it appears to be so.
My current client has this happening when opening a project file that was
created in 2003, but modified in 2007 and then saved back to 2003.
Not sure if all instances of the problem are because of version issues.
Does anyone know why this is happening, and how to prevent or fix it?
Project 2003 files seem to randomly delete the data from tasks, so that the
entire task row becomes blank. Filtering it does not show the task as
actually blank, but it appears to be so.
My current client has this happening when opening a project file that was
created in 2003, but modified in 2007 and then saved back to 2003.
Not sure if all instances of the problem are because of version issues.
Does anyone know why this is happening, and how to prevent or fix it?