A
Alex Zimmerhaven
Hi everybody. Hope you are all having a good day. Quick question - I have a
group of users that currently have Project 2007 installed (they just got it
installed). Unfortunately, my lab and curriculum is for 2003. Now, they are
just going to be using the most basic elements of project - nothing too, too
fancy. Working with tasks, creating resources, printing stuff, views, that's
it. They don't have project server or anything of that question. I'm only
going to be training them for 3 hours.
So, the big question is this - Can I just go ahead and train them on my
Project 2003 machines? Or should they wait until I upgrade to 2007.
Thanks again to all of you out there that post such valuable information!
Thanks,
Alex
group of users that currently have Project 2007 installed (they just got it
installed). Unfortunately, my lab and curriculum is for 2003. Now, they are
just going to be using the most basic elements of project - nothing too, too
fancy. Working with tasks, creating resources, printing stuff, views, that's
it. They don't have project server or anything of that question. I'm only
going to be training them for 3 hours.
So, the big question is this - Can I just go ahead and train them on my
Project 2003 machines? Or should they wait until I upgrade to 2007.
Thanks again to all of you out there that post such valuable information!
Thanks,
Alex