V
Vic
Hi,
Myself and another Project Manager are working on a plan. She has Project
2007, I have 2003. She saves the plan as 2003. But when I open a plan that
she has updated the dates have moved (Imp date has moved almost a month).
Any ideas on what would cause this? It may not be a 2007 vs 2003 issue, but
that was my first thought (we made sure our leveling parameters were the
same).
Myself and another Project Manager are working on a plan. She has Project
2007, I have 2003. She saves the plan as 2003. But when I open a plan that
she has updated the dates have moved (Imp date has moved almost a month).
Any ideas on what would cause this? It may not be a 2007 vs 2003 issue, but
that was my first thought (we made sure our leveling parameters were the
same).