Project 2003 - Web - Time Sheet View - Show day of week + date

P

paulgent

Project 2003 Server - Web Access

Hi,

Is it possible to customise the Time Sheet View to display the day of
the week text i.e. Monday, Tuesday (or abbreviated to Mon, Tue etc -
I'm not picky!) etc as well as the date ? If so - How ?

I know I can customise the left side view (Displayed Fields) but cannot
see how to modify the column titles in the right side.

TIA,

P.
 
P

paulgent

Solved.

Found the answer in the following posting :

PWA timesheet column header

"You must have view options show days of the week and only have 7 days
or less showing at one time for the days of the week to show up along
with the date."
 