Mark Taylor
I recently started having an issue with MS Project Professional 2003. If I link two detail tasks together, the link shows up, but the second task will not move out after the completion of the first task, i.e., a standard FS dependency. Also, if I create a summary task for several detailed tasks, the duration of the summary task will stay at 1 day even if the detailed tasks have a duration of several days. I haven't changed any config settings and if I give the mpp file to a coworker, everything works as one would expect. When she saves the file and sends it back to me, it looks as I would expect it to, but if I modify anything, like insert a new detail task, the detailed taskss don't move out, nor does the summary task reflect that the duration has increased. If I manually adjust the detailed tasks, the summary task still will not update correctly.
I suspect that either an OS (XP) update or Office (2007) update may have overwritten a dll. A repair install and two uninstall/re-installs of Project did not fix the problem.
EggHeadCafe - Software Developer Portal of Choice
WPF And The Model View View Model Pattern
http://www.eggheadcafe.com/tutorial...b-7374d3da3425/wpf-and-the-model-view-vi.aspx
I suspect that either an OS (XP) update or Office (2007) update may have overwritten a dll. A repair install and two uninstall/re-installs of Project did not fix the problem.
EggHeadCafe - Software Developer Portal of Choice
WPF And The Model View View Model Pattern
http://www.eggheadcafe.com/tutorial...b-7374d3da3425/wpf-and-the-model-view-vi.aspx