S
scparker
Hello,
I am updating a lot of project files within the company and one aspect
that needs updating is the Actual Finish Date. The Project has a
planned Start Date and a planned Finish Date. These must remain as
they are. However, when I add the Actual Finish Date to the project,
it amends the Finish Column as well. I do not want it to do this.
Why does it do this and how may I be able to stop it from doing this?
Sincerely,
Stephen
I am updating a lot of project files within the company and one aspect
that needs updating is the Actual Finish Date. The Project has a
planned Start Date and a planned Finish Date. These must remain as
they are. However, when I add the Actual Finish Date to the project,
it amends the Finish Column as well. I do not want it to do this.
Why does it do this and how may I be able to stop it from doing this?
Sincerely,
Stephen