Hi,
Thank you for posting and welcome to this Microsoft Project General
Questions discussion group.
In addition to Jan's advise:
1.- You can use the "Assign resources" dialog box (ALT+F10), select the
resources you want to view, click on the "Graphs..." button. select "Work" on
the drop-down list (work=effort).
2.- You could also use the "Visual reports", selecting the "Resource Work
Summary Report" and then in Excel, customize the dynamic graph to fit your
needs.
I hope this helps. Please, let us know how you get along with it.
Best regards,