Looking for suggestions on how to best represent the level of effort for a
project visually - using Gannt chart?
 
J

Jan De Messemaeker

Hi,

One thing is for certain: the gantt Chart is not the best representation for
a level of effort
Try the resoruce usage or the resource graph views.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

José Miguel Piñeres

Hi,

Thank you for posting and welcome to this Microsoft Project General
Questions discussion group.

In addition to Jan's advise:
1.- You can use the "Assign resources" dialog box (ALT+F10), select the
resources you want to view, click on the "Graphs..." button. select "Work" on
the drop-down list (work=effort).
2.- You could also use the "Visual reports", selecting the "Resource Work
Summary Report" and then in Excel, customize the dynamic graph to fit your
needs.

I hope this helps. Please, let us know how you get along with it.