S
StephenB
We are in a business with fixed start and end times for all tasks. There is
no such thing as early, late, less or more effort, overtime, no split tasks,
(recources we have but as a pool, not as individuals), we don't track costs
in this manner, etc. Everything is an FS task.
We nonetheless like the graphical look of a plotted-out Project schedule to
use and show clients for intent or we would use Excel.
I am having trouble "tricking" the functions of the program to get visual
results. For instance, I have to make up a "false" task to start every
project so my real first task can have a predecessor. I'm having trouble
getting a series of tasks linked by start/finish dates with milestones at
most junctures to come out as tasks - often all I get is a thin dark line
from milestone to milestone, other times I get a real Task line graphic.
It's true, I do not know how to use the program on the level it was written
for - but there must be some out there who can relate to this issue and pass
on a few tips?
Thankful, StephenB
no such thing as early, late, less or more effort, overtime, no split tasks,
(recources we have but as a pool, not as individuals), we don't track costs
in this manner, etc. Everything is an FS task.
We nonetheless like the graphical look of a plotted-out Project schedule to
use and show clients for intent or we would use Excel.
I am having trouble "tricking" the functions of the program to get visual
results. For instance, I have to make up a "false" task to start every
project so my real first task can have a predecessor. I'm having trouble
getting a series of tasks linked by start/finish dates with milestones at
most junctures to come out as tasks - often all I get is a thin dark line
from milestone to milestone, other times I get a real Task line graphic.
It's true, I do not know how to use the program on the level it was written
for - but there must be some out there who can relate to this issue and pass
on a few tips?
Thankful, StephenB