Project 2007 Crashes when inserting column

J

Jack Dahlgren

Some more information might help here.
What is the column you are inserting? Is there a formula associated with it?
Is there a look-up table associated with it? What is it named? Does it
roll-down to the assignment level?

Second, what is the task sheet view? Is it a view you have created or is it
what you call the task usage view? Is it a local view or an enterprise view?

I'd start by going into the organizer and deleting any local views and
tables in the project that has a problem. Then I'd close project and delete
the folders which contain the cache. Then restart project and see what
happens.

-Jack Dahlgren
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top