L
Luca
Hi- I produced a programme for my client and he has come back and asked me to
add extra columns and features to the programme. They are as follows:
2. We appreciate that the start stop dates provided are ABCs view of how XYZ
should have tackled this project from the start, please add in columns for
XYZ's start stop dates and use say a dotted outline to reflect the bar to
differentiate it from the solid bar you have used to reflect ABC's start stop
bar.
3. Add in a solid bar in black narrower than the ABC start stop bar to
reflect when XYZ started the task and when they finished the task. Add two
columns after the 2 additional XYZ start stop columns to show the % complete
and the number of calendar days they are ahead or behind using a green for
ahead and red for behind with respect to ABC's start stop dates.
Much appreciated if someone knew how to do the above requests, I'm lost at
how I should do this? Your suggestions will be greatly appreciated.
add extra columns and features to the programme. They are as follows:
2. We appreciate that the start stop dates provided are ABCs view of how XYZ
should have tackled this project from the start, please add in columns for
XYZ's start stop dates and use say a dotted outline to reflect the bar to
differentiate it from the solid bar you have used to reflect ABC's start stop
bar.
3. Add in a solid bar in black narrower than the ABC start stop bar to
reflect when XYZ started the task and when they finished the task. Add two
columns after the 2 additional XYZ start stop columns to show the % complete
and the number of calendar days they are ahead or behind using a green for
ahead and red for behind with respect to ABC's start stop dates.
Much appreciated if someone knew how to do the above requests, I'm lost at
how I should do this? Your suggestions will be greatly appreciated.