I
I_Need_Help
Hi
I'm using the following to edit working days per resource it adds the days
but leaves the event name blank, what do I call to set the days name?
Eg if you open the resource calendar in MSP the Name field.
Microsoft.Office.Interop.MSProject.Application projectProApp = new
Microsoft.Office.Interop.MSProject.Application();
projectProApp.Application.ResourceCalendarEditDays(projectProApp.Application.ActiveProject.Name,
"MyTest", startDate, startDate, Missing.Value, Missing.Value, Missing.Value,
Missing.Value, Missing.Value, Missing.Value, Missing.Value, Missing.Value,
Missing.Value, Missing.Value, Missing.Value, Missing.Value, Missing.Value);
I'm using the following to edit working days per resource it adds the days
but leaves the event name blank, what do I call to set the days name?
Eg if you open the resource calendar in MSP the Name field.
Microsoft.Office.Interop.MSProject.Application projectProApp = new
Microsoft.Office.Interop.MSProject.Application();
projectProApp.Application.ResourceCalendarEditDays(projectProApp.Application.ActiveProject.Name,
"MyTest", startDate, startDate, Missing.Value, Missing.Value, Missing.Value,
Missing.Value, Missing.Value, Missing.Value, Missing.Value, Missing.Value,
Missing.Value, Missing.Value, Missing.Value, Missing.Value, Missing.Value);