Project 2007 non-working days

J

Jim19382

I am working with Project 2007 Professional. Is there a way to view and/or
print a list of non-working days for a base calendar or resource calendar?
 
R

Rod Gill

You need to loop thru each day in a calendar for the date range you are
interested in and test its Working property.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




Jim19382 said:
I am working with Project 2007 Professional. Is there a way to view
and/or
print a list of non-working days for a base calendar or resource calendar?

__________ Information from ESET Smart Security, version of virus
signature database 4597 (20091111) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4597 (20091111) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top