I have several users who, after they approve task updates, do not see the
actual hours just approved. If we do a Task Usage view, the actual hours
columns are blank. What is causing this and how do I correct it. Weare
using Project Pro SP1 2007 and MOSS/Project server 2007. PLEASE HELP!
Thanks.c
You may be encountering a bug. The fixes below are listed as part of
the "August Cumulative Update" at
http://support.microsoft.com/kb/956061
Excerpted fixes that may help you (there are another ~30 fixes listed
above that I'm not including here.):
• After a resource updates a task, the updated actual billable work is
not displayed in the cube report.
• The work that is accepted on the Task Updates page may not appear in
the project when the update is applied.
• When all plans are successfully published, actual work information
is missing in the reporting database.
• In PWA, you lock a task on the Close Tasks to Update page. However,
you can still add that task by using the Add Tasks feature on the My
Tasks page and submit actual work.
• When resources submit actual work to their project managers, the
first day of the timephased actual work is moved into a different
week.
• After you apply hotfix 941426, the actual work that was accepted by
the project manager is not updated into the project plan.
• When you post actual work for a single resource for a task that has
more than 5 resource assignments, the update to Project Server fails.
Additionally, the Unified Logging Service (ULS) throws the following
exception:
Exception occurred in method Statusing.UpdateStatus
System.ArgumentException: These columns don't currently have unique
values.
• A project manager accepts the actual work. However, the actual work
is not updated into the project plan.
Despite the name, this update was very recently released. Proceed
cautiously and with lots of testing.
James Fraser