A
AndyW
Hi folks, apologies if this question has already been asked before.
I have a project (with appropriate baseline) and have a task with an
estimate for 2 days duration (estimated duration). The task is taking 3
days and probably longer, however, when I enter in 3 days for "actual
duration", project marks the task complete and increases the estimate to 3
days.
I can do a view.tables.variance to see what the original work was as per the
baseline - which is one way of doing things.
What I actually want is for project to not change the original estimate to
the actual work performed (as I need these original estimate values) and I
really dont want it to mark tasks complete when they are not - on my project
tasks are completed when deliverables are signed off, not because some
arbitary piece of time has elapsed.
Is it possible to do this in project?
Regards
Andy
I have a project (with appropriate baseline) and have a task with an
estimate for 2 days duration (estimated duration). The task is taking 3
days and probably longer, however, when I enter in 3 days for "actual
duration", project marks the task complete and increases the estimate to 3
days.
I can do a view.tables.variance to see what the original work was as per the
baseline - which is one way of doing things.
What I actually want is for project to not change the original estimate to
the actual work performed (as I need these original estimate values) and I
really dont want it to mark tasks complete when they are not - on my project
tasks are completed when deliverables are signed off, not because some
arbitary piece of time has elapsed.
Is it possible to do this in project?
Regards
Andy