B
Bilal
Hello masters and happy new year for you all, as you see, I am very new
guest to this group and I liked the high level of experience I found it here
I am in the middle of getting hands on experience in MS Project and came up
with couple of questions
1. After I installed, deployed and customize the Project Server 2007 in my
organization I have been asked to re-do the whole thing again in different
server and the old one is going to get formatted, Is there a way to export
all the customized data (global custom fields, enterprise resources, lookup
tables, standard and customs calendars, timesheets, etc ) from one server to
another?? And how if possible
2. If the project manager approved a task, is it possible to re-open it
again and send it back to the team members to re-do the work again (if the
project manger decide that the work is not done properly)?? Is it a good
project management practice??
3. Regarding baselines, who is authorized to set it or change it, can I make
it only a job of the executive?? Our senior management doesn’t want the
project manger to overwrite the old one and they need him to refer to them if
the baseline needs to be changed
4. Can you guide me on how to start developing new reports that summarize
the content of all the timesheets submitted by all the team members (for
example total hours per project, total hours per timesheet category, total
hours per team, etc) , just give me the start point and I will dig through
the details
5. Can I develop one view for the executive to show the status of all the
projects (CPI, SPI, Actual cost, EV, etc)
I don’t want to be so annoying by putting more questions but I hope the
answers will help the others also
--
Best Regards
Bilal Okour
blog : http://ebilal.spaces.live.com
guest to this group and I liked the high level of experience I found it here
I am in the middle of getting hands on experience in MS Project and came up
with couple of questions
1. After I installed, deployed and customize the Project Server 2007 in my
organization I have been asked to re-do the whole thing again in different
server and the old one is going to get formatted, Is there a way to export
all the customized data (global custom fields, enterprise resources, lookup
tables, standard and customs calendars, timesheets, etc ) from one server to
another?? And how if possible
2. If the project manager approved a task, is it possible to re-open it
again and send it back to the team members to re-do the work again (if the
project manger decide that the work is not done properly)?? Is it a good
project management practice??
3. Regarding baselines, who is authorized to set it or change it, can I make
it only a job of the executive?? Our senior management doesn’t want the
project manger to overwrite the old one and they need him to refer to them if
the baseline needs to be changed
4. Can you guide me on how to start developing new reports that summarize
the content of all the timesheets submitted by all the team members (for
example total hours per project, total hours per timesheet category, total
hours per team, etc) , just give me the start point and I will dig through
the details
5. Can I develop one view for the executive to show the status of all the
projects (CPI, SPI, Actual cost, EV, etc)
I don’t want to be so annoying by putting more questions but I hope the
answers will help the others also
--
Best Regards
Bilal Okour
blog : http://ebilal.spaces.live.com