C
Carl
I am running Project locally, not on a server.
Suppose I want all of the tasks to be changed to 7.5 hr calculation or 37.5
hr week. Will it work to assign the entire project and sub-tasks all to 7.5
hrs/37.5 hr week or do I need to do all individual tasks that way?
In other words, what’s the highest level that I can set the tasks to this
setting?
And what is the best way to do this?
Suppose I want all of the tasks to be changed to 7.5 hr calculation or 37.5
hr week. Will it work to assign the entire project and sub-tasks all to 7.5
hrs/37.5 hr week or do I need to do all individual tasks that way?
In other words, what’s the highest level that I can set the tasks to this
setting?
And what is the best way to do this?