Hi Suzy,
From the sounds of what you have going on, I'd be confused as
well -- so don't worry.
Let's start back at the beginning -- you say you're using Project
2007 without Project server and IT has installed some updates -- I
assume Service Pack 1 for Project 2007. That SP is a good start.
Your leveling calculation is set to manual so that should not be
changing any other resource assignments if you modify another
assignment so we can rule that out.
The oddities appear only when you are updating progress on tasks?
If you look at a task which has been changed by updating another
task what does it show in the Task Usage view? For remaining work
to have been increased so wildly I assume you have multiple
resources assigned? In the Task Usage view add the Assignment Units
field to the left side -- I assume assignment units for the
resources are incredibly high?
A couple of other things to check:
No resources assigned to summary tasks
No links between summary tasks
It's possible the project file has become corrupt for whatever
reason. On a copy of the file, try saving as an XML file. Exit
Project and import the XML file to see if that fixes it.
If you'd like you're welcome to send me the file. I'll take a look
and see if there is anything that jumps out at me. Send to
prjngATmaine.rr.com replace the AT with @.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Suzanne said:
Hi Julie,
Thanks for your reply.
Sorry for not explaining my problem clearly...to be honest I'm
very confused!
I have checked and confirm levelling is set to manual calculation.
I also
don't believe it has anything to do with levelling or predecessors
/
successors as that does not explain why the work (effort) attached
to a
resource increases dramatically on a task not being updated.
Unfortunately my issue does not seem to hold any logic, one
example is:
When I Progress Schedule (Tools, update project) the remaining
work on a
task increased from 94.57hours to 4726.67hours and in this case
the Finish
date changed only slightly from 6Mar09 to 20Mar09.
This is not isolated to using the 'update project' feature as
remaining work
and finish date also randomly change on tasks when updating other
details on
another task.
Our IT installed some updates overnight but we are still having
problems.
It seems to me like it's a bug but if that was the case I would
have thought
other people would be experiencing the same issues.
Once again any help you can provide is greatly appreciated.
Thanks,
Suzy
<snip>