Project 2007: Time report to plan update automatically

E

Edward Wang

I found the process of time report to project plan update is pretty
difference between project 2007 and project 2003.
In project 2007, we need resource to fill the timesheet ---> submit it --->
get approval --> import to the task page ---> submit it ---> PM accept it.

It is too complicated. I have found way to make the timesheet report
approval automatically, and any one could tell me how to make other steps
automatically.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top